Project Site Plan/Engineering
The project will consist of off-shore facilities for unloading LNG carriers, and on-shore facilities for storing LNG, vaporizing the LNG, and sending out the natural gas at a baseload rate of 500 million standard cubic feet per day (mmscfd), with peaking capacity of approximately 625 mmscfd.
Upon vaporization, the natural gas will be sent via an approximately 30-mile pipeline (up to 30-inch diameter) to the interstate natural gas pipeline system of Maritimes and Northeast Pipeline (M&NE) at its existing compressor station at Baileyville, Maine.
Key characteristics of the project include
- 500 mmscfd baseload facility with 625 mmscfd peak capacity, and expandable to 1 bcfd capacity
- Natural water depth of 50 feet MLLW – no dredging required
- Two 160,000 m3 (net) capacity full containment LNG storage tanks
- Initial LNG Carrier range of size from 70,000 m3 to 165,000 m3
- Expected delivery of one LNG Carrier weekly
- Water bath regasification units
- Gas pipeline lateral of approximatly 30 miles (up to 30” diameter)
- No NGL extraction
- No LNG trucking

|